Vernon County Landfill faces uncertain future with legal challenges, local hauler buyout that compounds DNR expansion delays

Oct. 21, 2026

VIROQUA, Wis.- The Vernon County Infrastructure Committee met recently to confront a major shift in the local waste hauling market that could reshape the long-term future of the Vernon County Landfill. Committee members and county staff discussed the news that Big Hook, one of the only remaining local waste haulers in the county that was still delivering trash to the county owned landfill, was recently bought out by GFL Environmental. GFL is an international corporation and the largest waste hauler operating in the region and sends the majority of its collected waste to a company owned landfill near Eau Claire.

The acquisition raises critical questions about incoming waste volumes and long-term financial stability at the Vernon County Solid Waste and Recycling facility in the Town of Viroqua. Only a few months earlier, at a March 17 joint meeting of the Finance and Infrastructure committees, Big Hook representative Mike Reschke had told county supervisors that his company remained committed to bringing its trash to the Vernon County Landfill as long as the facility stayed open and maintained competitive pricing.

“We fully support the landfill, as long as they keep the landfill open,” said Reschke. “If the landfill stays open at their current rate that they are charging, we keep bringing our trash. That’s just the way it is.”

At that same meeting, Reschke noted that his company had researched backup disposal options only because of the prolonged uncertainty surrounding whether the county facility would run out of room and close on short notice.

“We have researched other options for backup, just in case the landfill is closed on short notice we have to have someplace else to go,” said Reschke. “And, of course, us, just like anybody else wants answers if you’re going to move forward or not.”

Now that GFL has purchased Big Hook, county officials anticipate that much of that waste stream could be routed through the private transfer station GFL operates in Viroqua and hauled over 100 miles away to privately run landfill near Eau Claire.

Big Hook/GFL truck – Tim Hundt photo

Short-term space relief versus long-term revenue risks

During the Infrastructure Committee discussion, Solid Waste Director Stacie Sanborn and committee members explained that losing volume from the Big Hook buyout may not have a significant impact initially on daily operations. Because the county facility is extremely tight on permitted airspace while waiting for a delayed expansion decision from the Wisconsin Department of Natural Resources, the department has already been purposefully diverting waste to prevent the current cell from filling up. Sanborn told the committee that recent operational data shows the landfill is already diverting a massive share of its normal trash flow to conserve room.

“Based on the last couple weeks worth of data I have, we’re estimating about 60 percent of our regular volume is being diverted,” said Sanborn. “If the county is pursuing an expansion, we have to conserve air space until we are approved to expand. Otherwise, if we reach full capacity, the landfill is then required to go into full closure.”

Former landfill manager Gail Frie, who stepped in as interim director over the summer while Sanborn was on leave, told the committee that state regulators recommended the diversion strategy and that having haulers take trash elsewhere temporarily is far less expensive than the county trucking waste out on its own.

“And diversion was a recommendation of DNR, and it’s also a much cheaper way to go rather than to try to transport waste out,” said Frie. “We would have cost us a fortune by doing this, with diverting that much it buys us enough time through the end of 2027 realistically.”

Supervisor Wayde Lawler noted during the discussion that this approach relies on private haulers choosing alternative disposal sites rather than the county directing where the garbage goes. Frie explained that allowing haulers to divert waste independently also protects the county from environmental liability at other disposal sites.

“If we direct it, then we maintain the liability for it,” said Frie. “If they do it on their own, we’re out of it.”

While the reduction in volume helps preserve scarce airspace in the short term, committee members and staff warned that the buyout could severely impact landfill revenues over the long term depending on what local cities, villages, and towns decide to do with their waste once an expansion decision is reached.

Township waste contracts and municipal participation

Sanborn discussed with the committee how many townships are currently sending waste to the facility and what municipal participation may look like in the future. The Vernon County Landfill service area covers 21 townships, nine villages, and three cities. According to the county feasibility report addenda, the county previously secured agreements with 21 of the 33 municipalities in Vernon County, representing roughly 80 percent of the county population, confirming their interest in using the county landfill.

However, county officials learned that some townships that had originally written requirements into their hauling contracts with Big Hook and other haulers mandating that their waste be taken to the Vernon County Landfill were later removed those provisions. The clauses were removed in case haulers needed flexibility to take trash to other facilities during the county period of waste diversion. Because those local disposal requirements were stripped from the contracts, GFL will not be required to bring the waste from many of those townships to the Vernon County facility and will be free to haul that trash out of the county.

GFL Viroqua transfer station – Tim Hundt photo

The removal of those township contract requirements follows an earlier decision by the Infrastructure Committee to suspend its own requirement that commercial haulers sign county contracts guaranteeing waste delivery to the Vernon County Landfill. Sanborn had explained to the committee that independent haulers could not commit to binding delivery contracts without knowing whether the county landfill would remain open.

“The bigger hauler that’s hauling us a majority of our waste right now doesn’t want to sign a contract,” said Sanborn. “He was uncomfortable signing a contract for all the garbage that he brings to continue to come to us in the event we don’t expand, or in the event we have to start doing waste diversion and things like that. And I don’t blame them.”

The county saw a similar shift earlier in 2026 with the City of Viroqua, which generates about 1,200 tons of waste annually, or roughly 12 percent of the landfill volume. In February 2026, the Viroqua City Council voted to amend and extend its hauling contract with GFL through the end of 2028, removing a clause that required the company to dump the city trash at the Vernon County Landfill. Beginning March 1, GFL began hauling Viroqua municipal waste to its Eau Claire facility, a move Sanborn described to the Infrastructure Committee as a mixed blessing that cost the department about $75,000 in annual revenue while saving 1,200 tons of needed airspace.

“It is a double edged sword,” said Sanborn. “It sucks for my budget, but it is buying us 1,200 ton of airspace for the rest of this year anyway.”

Sanborn explained to the committee earlier in the year that rural townships have historically been the most loyal supporters of the county solid waste system because the county provides free recycling services to participating towns, whereas cities and most villages pay private haulers for recycling collection.

“We provide their recycling service so they’re more on board to keep that stuff going, because we’re doing it for free right now,” said Sanborn. “Whereas the City of Viroqua, the City of Hillsboro, all the villages except for La Farge, pay for that service as it is.”

Township leaders have repeatedly urged the county board and the Infrastructure Committee to keep the local landfill open so rural communities are not left at the mercy of corporate haulers. Town of Forest Chairman Mark Davison, who also chairs the Vernon County chapter of the Wisconsin Towns Association, told the committee that local towns strongly back the facility and warned that higher private disposal rates would lead to illegal dumping along rural roads.

“What are we going to do with their garbage, sure, haul it somewhere else,” said Davison. “If the cost gets too high, people are going to throw their garbage in the ditches. Years ago, that’s what people did.”

County Board Chair and Infrastructure Committee Chair Lorn Goede also argued that keeping the facility open is vital for local economic control, pointing out that private haulers like GFL still try to use the county landfill for difficult loads they do not want to truck to Eau Claire.

“We turned down stuff from GFL right now because they want to bring us their crap that they don’t want to haul to Eau Claire,” said Goede. “They want to bring us their tires. They want to bring us their deer bones and they want to bring us their asbestos that we turn down because lack of airspace right now.”

Vernon County Solid Waste and Recycling facility on County Road LF – Vernon County photo

Goede contended that once the expansion is built, hauling economics will bring waste volumes back to the Vernon County facility.

“You cannot tell me it is cheaper to bring it to Viroqua, dump it off, reload it and haul it 150 miles with a $200,000 machine,” said Goede.

Frie agreed that if the county expands and keeps its tipping fee competitive, municipalities will direct their waste back to the county facility and new independent haulers will emerge.

“All municipalities, businesses, citizens have the legal right to direct the waste to the landfill that they own,” said Frie. “As long as the Vernon County landfill is competitively priced, there will be new garbage collection company startups who will be more than willing to use the local landfill. This has happened many times in the past.”

Other supervisors expressed skepticism that the county can easily recover lost tonnage after GFL consolidates local hauling routes. Jacobson questioned how much of the county roughly 20,000 tons of annual waste GFL now controls and how long it would take to win any of that business back.

Vernon County District 11 Supervisor Charles Jacobson – Vernon County photo

“So if there’s 20,000 tons in Vernon County, how much is GFL taking out of that right off the top?” said Jacobson. “It’s going to take time to get it back here. Even if we do, there’s still going to be a stagger.”

Supervisor Martha Olson raised similar concerns that reduced municipal tonnage will force the county to raise its $65 per ton tipping fee, undermining its price advantage.

“With the City of Viroqua not bringing their garbage, now we’re at 8,000 ton, when we need 15,000 to make a profit,” said Olson. “I don’t think there’s any way we can keep prices as they are right now and remain profitable.”

An eight year battle with the DNR over expansion approval

The current squeeze on airspace and hauler contracts stems from a battle to secure DNR expansion approval that has dragged on since 2018. The existing landfill opened in 1993 after state regulators mandated the closure of 25 unlined local town, village, and city dumps across Vernon County. For decades, the landfill received between 15,000 and 20,000 tons of trash per year while operating as a self funded enterprise without county property tax levy support.

However, volumes and revenues began fluctuating after Southwest Sanitation was sold to GFL and the county corporation counsel advised that the county flow control ordinance was unenforceable. In late 2018, in an effort to keep the largest hauler from taking trash out of the county, a previous county board chair and solid waste committee cut the landfill tipping fee from $60 per ton down to $49 per ton. Frie told the Infrastructure Committee that because state law requires municipal landfills to charge the same gate rate to all customers, that decision drained over $1.1 million in revenue just as the department was starting the expansion process.

“In late 2018 under the direction of a prior county board chairman, this committee decided to lower the tipping fee to $49 a ton,” said Frie. “At today’s rate, that costs the landfill $1,111,899.75. That pretty much tells the story of why we’re in financial trouble right now.”

When GFL later ended that arrangement and began shipping its waste to Eau Claire, receipts at the Vernon County Landfill dropped from 18,415 tons in 2023 to 12,336 tons in 2024 and 9,323 tons in 2025.

Vernon County Landfill – contributed photo

Meanwhile, the technical permitting process with the DNR encountered repeated roadblocks. Although the department first sought permission to begin a feasibility study in 2018, engineering firm Short Elliott Hendrickson was not authorized to submit an initial site inspection request until late 2020. In May 2021, test borings found shallow bedrock west of the active landfill, forcing engineers to redesign the project as an eastern and vertical expansion that adds 4 acres horizontally and 5 acres vertically for 427,355 cubic yards of capacity.

The County Board approved pursuing the 15 year expansion on a 14 to 3 vote in October 2023 and submitted a 2,368 page feasibility study to the DNR. However, the DNR issued a first notice of incompleteness in December 2023 and a second notice of incompleteness in March 2025, questioning how groundwater could be monitored in the fractured carbonate karst bedrock beneath the site. In January 2025, the County Board voted 19 to 0 to keep pursuing the expansion and asked state legislators to help mediate the impasse. To satisfy state hydrogeologists, the county spent $130,000 to drill additional monitoring wells, conducted quarry rock face surveys with the Wisconsin Geological and Natural History Survey, and paid $15,000 to $20,000 for additional hydraulic slug testing in March 2026. Frie expressed frustration to the committee in June 2026 that the engineering costs had climbed to nearly $1 million.

“This is the third feasibility study done on the site,” said Frie. “The county asked for permission to start the feasibility in 2018 and got permission to proceed in 2020, so we started two years too late. The first draft went to DNR at a cost of $375,000, and now we’re almost at $1 million with nothing to show for it.”

Former Vernon County Solid Waste Administrator and now Interim Administrator Gail Frie – Tim Hundt photo

Because of the prolonged permitting delays, an airspace survey in early 2026 showed the existing landfill had only 18,194 cubic yards of remaining space, much of it buried beneath thick layers of intermediate soil cover that must be excavated with a bulldozer to reclaim.

“If we make no effort to recover this airspace we will be closing,” said Sanborn. “We filled 18,000 cubic yards of dirt instead of garbage that could have generated revenue.”

On August 17, 2026, the county finally cleared a major regulatory hurdle when the DNR issued an official determination of completeness for the feasibility study, initiating a 30 day public comment period.

Coming down to the wire with town host negotiations and legal challenges

Even with the completeness letter in hand, the expansion effort is likely to come down to the wire as the county faces a stalled Town Host Agreement negotiation, a contested case hearing requested by a citizens group, and a lawsuit in Vernon County Circuit Court.

Under Wisconsin Statute Section 289.33, the county is required to negotiate a Town Host Agreement with the Town of Viroqua to address local operational impacts, road maintenance, well testing, and host fees. When the landfill opened in 1993, the county and township relied on an informal handshake arrangement rather than a written contract. In April 2025, the Town of Viroqua Landfill Siting Committee, chaired by landfill neighbor AnnaJo Doerr and represented by attorney Anders Helquist, submitted a 32 page proposed agreement calling for strict groundwater contamination liability stopgaps, property value protections, local enforcement penalties for garbage trucks violating designated haul routes, and a firm 15 year closure date. Doerr told supervisors that residents in the township want binding operational safeguards.

“I just want to remind the board that this long history of operating a landfill has never had on record a written agreement with the Town of Viroqua as the town host,” said Doerr. “And so, with the town host agreement that is not yet on record, and now the Town of Viroqua has legal counsel helping negotiate that, there are some requests that are being asked from the Town of Viroqua which are still not in any plan.”

Negotiations stalled in early 2026 after the Infrastructure Committee countered with a 15 page draft modeled on a La Crosse County agreement that removed many of the town demands and included a clause allowing the county to terminate the agreement with 60 days notice if the landfill stopped taking waste. Helquist objected to that clause during a joint negotiation session, calling it a loophole that could strip the town of protections.

“You guys can stop accepting waste for a week and terminate this if you run out of capacity,” said Helquist. “You can just terminate this agreement. You can terminate the town host payment. You can terminate any protections that are negotiated.”

Big Hook dumpster at the Vernon County Fairgrounds – Tim Hundt photo

Neighbors have also pressed the committee on truck traffic and odor concerns during the host agreement talks. Kyle Kruizenga, who lives adjacent to the landfill on County Road LF, told the committee that garbage and recycling trucks frequently ignore the mandated haul route of U.S. Highway 14 to County Road Y to County Road LF.

“The only route to and from the Vernon County Landfill by contract is (county road) LF to (county road) Y to (state hwy) 14,” said Kruizenga. “That is what you agreed to, and you’re not following it.”

At the same time, a group of local citizens, Friends of Vernon County Waters, opposed to the expansion has formally organized, hired an attorney, and filed for a contested case hearing with the DNR. An action has also been filed in Vernon County Circuit Court challenging the county actions regarding the landfill. Throughout the public meetings, opponents including Tom Lukens and retired geologist Kelvin Rodolfo have argued that the site karst geology threatens local groundwater and trout streams, pointed to past DNR notices of non-compliance regarding daily cover and leachate management, and challenged whether there is a legitimate need for the expansion given the drop in local waste tonnage.

“The statute prohibits the department from approving a feasibility report for a proposed facility unless its proposed capacity is designed to be consumed within 15 years,” said Lukens. “The department will evaluate the need for the proposed expansion and projected site life, and provide determination on both in the feasibility determination. There hasn’t been a feasibility determination, folks. The need isn’t there.”

At the recent Infrastructure Committee meeting, staff explained that the DNR told the county that agency officials are not certain what the contested case hearing process will entail or how long it will take to resolve.

Under Wisconsin Statute Section 289.27, within 30 days after the DNR publishes public notice that a feasibility report is complete, a municipality, an applicant, or any group of six or more persons may request a contested case hearing if they have a substantial interest to be protected and demonstrate a dispute of material fact. Unlike a standard informational hearing where the public simply submits comments, a contested case hearing is a formal, trial like administrative proceeding overseen by an administrative law judge from the state Division of Hearings and Appeals. The hearing allows parties to present expert witnesses, cross examine engineers and hydrogeologists, and submit legal briefs on technical issues of site feasibility, environmental safety, and the statutory need for the landfill. State statutes specify that the Division of Hearings and Appeals must schedule the hearing to begin within 120 days after the 30 day comment period expires, and the DNR must issue a final feasibility determination within 90 days after the hearing is adjourned, though prehearing discovery and legal motions can extend the overall duration of the proceeding.

Legal filings and environmental concerns at infrastructure committee meeting

During a recent Vernon County Infrastructure Committee meeting, KJ Jacobson, speaking as a resident of Viroqua and a representative of the newly formed association Friends of Vernon County Waters, updated officials on the legal actions taken against the county landfill expansion. Jacobson stated that the association quickly grew to 100 members and retained legal counsel to challenge the project, noting that “several of us formed an association called Friends of Vernon County Waters” and “we have an attorney representing us”.

Jacobson explained that the group initiated three formal filings, including an action in Vernon County Circuit Court and a petition to the Wisconsin Department of Natural Resources (DNR) for a contested case hearing. According to Jacobson, the DNR granted the contested case hearing request in “a day and a half”. Following that decision, the group’s circuit court filing was temporarily put on hold by mutual agreement. Jacobson clarified the status of that court action, stating that “a different lawyer who deals with the Circuit Court, asked us if we would stay that filing to the circuit, Vernon County Circuit Court, until the contested hearing is over, and we agreed to that”.

Detailing the upcoming proceedings, Jacobson noted that the matter has moved out of the DNR’s hands and is waiting for an administrative law judge to be assigned by the state Division of Hearings and Appeals. Jacobson described the formal nature of the upcoming litigation, explaining that “there’ll be discovery interrogatories sent to various people involved, requests for production of documents, and there may be depositions”. Emphasizing the gravity of the forum, Jacobson added that “a contested case hearing is very much like a circuit court trial” where “there’s no jury, but it’s formal” and “witnesses are under oath; they can be cross-examined”. Jacobson pointed out that the entire administrative challenge could be avoided if the county chose a different path, noting that “if you decide to withdraw the feasibility application, then of course the contested hearing goes away”.

Beyond challenging the feasibility and the official determination of need, particularly in light of the recent buyout of independent hauler Big Hook by GFL Environmental, Jacobson stated that preparing for the legal battle revealed deep-seated operational failures. Jacobson told the committee that “in the course of preparing to challenge the feasibility, we have discovered a lot of very bad management of the landfill”. Pointing to an email previously sent to supervisors detailing 25 separate types of recurring violations involving special waste and leachate management, Jacobson stressed that proper liquid containment is paramount stating “leachate management is the most important element of protecting the groundwater, and it has not been done”.

Proposed landfill budget and cost cutting amid delays

Given the ongoing permitting delays and the sharp reduction in waste volumes, Sanborn presented a proposed budget and operational plan for the landfill focused on cutting costs until a final expansion decision is reached. To trim expenses and align operations with reduced incoming tonnage, Sanborn has implemented cost cutting measures, including reducing staffing costs by replacing full time personnel with part time help and deferring major capital spending while diverting trash.

In her financial report and revised budget projections, Sanborn also addressed a notable adjustment in the leachate hauling budget, which increased from $30,000 to $155,000. When Olson asked about the jump from $30,000 to $155,000, Sanborn explained that the county historically employed a full-time staff member to haul leachate with a county truck, but after the truck experienced mechanical problems over the summer, the department contracted the hauling out. Sanborn told supervisors she is continuing the contracted hauling in the budget because it actually costs the department less overall than maintaining a county truck and paying a full-time driver to haul the liquid.

Additionally, because the county is diverting roughly 60 percent of its waste stream rather than burying it on site, the landfill is reducing what it pays in state environmental and recycling surcharge fees, which cost $13.15 per ton and normally account for $100,000 to $130,000 in the budget under licenses.

Even with those operational adjustments, the solid waste enterprise fund faces significant financial pressure after recording net losses of $165,000 in solid waste and $30,000 in recycling, alongside roughly $250,000 in annual depreciation and a $674,000 audit adjustment for long-term care obligations. The department also carries general fund loans of $430,000 for additional expansion engineering studies and $90,000 for compactor repairs. If the DNR approves the feasibility study and a subsequent Plan of Operations, borrowing to construct the three proposed expansion cells is estimated to cost between $2.8 million and $4 million.

Vernon County Board Chair Lorn Goede – Tim Hundt photo

Supporters of the expansion, including Frie and Goede, have argued that borrowing $3 million to $4 million is a sound investment because the new cells will generate an estimated $20 million to $30 million in total tipping fee revenue over their 15 year life, leaving at least $20 million for local operations after $8 million in state DNR fees are paid.

“If someone comes to me with a $3 million investment that over the next few years is going to bring in $25 million I really take a serious look at it,” said Goede. “Because that is what we are investing in.”

However, Jacobson and Lawler have insisted that the Infrastructure Committee and County Board must conduct a rigorous financial analysis before committing millions of dollars in new debt, especially with GFL buying out independent haulers.

District 14 County Supervisor Wayde Lawler

“But that doesn’t mean you’re going to send $3 million into something where you still don’t know if you’re going to get approval,” said Jacobson. “We’re guessing at numbers.”

Lawler told the Infrastructure Committee at a previous meeting that supervisors have a duty to evaluate whether the expansion remains financially viable even if the DNR grants a permit, focusing on operating results per ton, changes in net position per ton, county cash support per ton, and projected annual cash surpluses or shortfalls.

“I think we have an opportunity and a responsibility to address everything from operations to does this remain a desirable path forward, even if the DNR approves it,” said Lawler. “Is that something we want to pursue based on what we have seen over the last two plus years of conversation about net position, about tonnage, about alternatives, all of those things.”

Administrative Coordinator Nate Torres told the board that he has been working with Sanborn to build a comprehensive 20-year budget model for the landfill based on a 20-year promissory note so supervisors can see all true operational, overhead, and debt service costs before a final decision is made.

Vernon County District 8 Supervisor Dave Eggen – Tim Hundt photo

“That’s a key component, is the debt service on the landfill expansion needs to go into the enterprise fund’s calculation of what their ongoing annual expenses are, not to mention payback on what they’ve already borrowed from the general fund,” said Torres. “And then finally, the conversation about is there additional revenue besides tipping fees that the county wants to talk about to subsidize the enterprise fund and for how long.”

That question of whether to subsidize the landfill with tax dollars if private haulers divert volume out of the county remains a central philosophical divide on the board. Supervisor Dave Eggen noted during the September board discussion that state law requires municipalities to provide safe garbage disposal and questioned why the landfill is expected to turn a profit when other county departments do not.

“I’ve always considered it to be a public service because the statute requires cities, towns, villages to have a safe way to handle their citizens’ garbage,” said Eggen. “We don’t expect, for instance, the sheriff’s department to show a profit and loss. We don’t expect human services to show a profit and loss. And all the departments in Vernon County, we don’t expect to see a profit and loss, but the landfill does.”

Oh, hi there. 👋 We are so glad you found us.

If you like our content maybe you want to sign up for our daily email. It's free and you won't miss any stories. One email a day with two or three top stories. It's like having your own personal newspaper. And we won't overload your inbox. Promise.

We don’t spam!

Tim Hundt

Add comment

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.